Westminster ADU Requirements in 2026: Pre-Approved Plans, Garage Conversions and Permit Steps

ADU, Remodeling and Room Additions in Orange County, CA

Westminster ADU Requirements in 2026: Pre-Approved Plans, Garage Conversions and Permit Steps

Exterior stucco brown coat on a new structure - Orange County

Westminster homeowners can start an ADU two ways: with a custom design, or with one of the city’s pre-approved standard ADU plans. This guide covers the Westminster ADU rules that matter most, how the standard plans work, and each step from pre-screening to permit.

CSLB #1149773Orange County, CAFree consultationEnglish & Tiếng Việt

Westminster ADU Rules at a Glance

  • How many: one ADU plus one Junior ADU (JADU) on a lot with a single-family home, plus the combinations state law allows.
  • State limits apply: 4 ft side and rear setbacks for new ADUs; a detached ADU can be at least 16 ft tall (18 ft near qualifying transit) and an attached ADU up to 25 ft.
  • Garage conversions: no new setbacks, and no replacement parking when the garage becomes an ADU.
  • Pre-approved plans: six detached standard plans from 781 to 1,240 sq ft (gross).
  • Fees: no park impact fee for an ADU under 750 sq ft.
  • Rentals: no short-term rentals of 30 days or less.

Westminster’s Pre-Approved ADU Plans

The City of Westminster offers six pre-approved standard plans for detached ADUs. Using one skips most of the custom design work, but not all of it: the city’s checklist says the standard plans are about 85% complete, so a design professional still prepares the site-specific sheets, such as the site plan, utility layout and energy forms.

Standard planGross sq ftNet sq ft
Plan 1781748
Plan 2A825791
Plans 3 and 41,036998
Plans 5 and 61,2401,198

Standard-plan applications go straight to the Building Division for plan check. Fees are paid when you submit, and incomplete packages are not accepted. Projects in a FEMA Special Flood Hazard Area can’t use the standard plans.

ADU great room framing and ceiling rough-in on a RealHomes Construction project in Anaheim, CA
ADU rough-in on one of our Anaheim projects. Standard plan or custom design, the framing, wiring and inspections follow the same building code.

Standard Plan or Custom Design?

A standard plan often fits when:

  • You want a detached ADU and one of the six layouts works for your family.
  • The lot is outside a flood hazard area and has room for the footprint plus setbacks.
  • You want to spend less time and money on design.

A custom design usually fits when:

  • You plan to convert a garage or attach the ADU to the house.
  • The lot is narrow, irregular or in a flood zone.
  • You need a specific layout, such as an accessible unit for aging parents or more bedrooms.

How the Westminster ADU Permit Process Works

ADUs are approved by city staff under state rules, without a public hearing. The city describes these steps:

DesignCheck feasibility, hire an architect or designer, and design to the Zoning Code and any flood zone rules.
Pre-screenMeet Planning, Engineering and Building at the counter (about 45 to 60 minutes, appointments encouraged), or upload to the Westminster Build online portal for comments within three business days.
Construction plansStructural, mechanical, electrical, plumbing and Title 24 energy sheets that meet the California codes.
Formal submittalADU-only projects can use one combined Zoning Clearance and Building plan check.
Permit and feesPlan check, permit and any park impact fee; ADUs under 750 sq ft pay no park fee.
Build and inspectCity inspections at each stage until the final sign-off.

If you go to the counter, arrive early: the city’s page notes the counter closes at 5:00 p.m. and turns away visitors who arrive within 30 minutes of closing.

Rules to Know Before You Build

Separate water meter

The city’s standard-plan packet requires a separate water meter for an ADU. A JADU shares the home’s meter.

No short-term rentals

An ADU can’t be rented for 30 days or less.

JADU owner rule

For a Junior ADU, the owner must live in the JADU or the main home, with a recorded deed restriction.

Fire sprinklers

Required in the ADU only if the main home requires them.

Easements

Plans must show every easement on the lot and include a note that the easements were verified.

Old unpermitted work

The packet says unpermitted work on the lot must be legalized or removed before a detached ADU permit is issued, so raise it early.

Some older Westminster handouts list a 16-ft height limit for attached ADUs. State law now allows attached ADUs up to 25 ft (or the zone limit, two stories max), so confirm the current numbers with Planning before you design.

Checklist Before You Contact the City

  1. Find your parcel number, lot size and zoning.
  2. Check whether the lot is in a FEMA flood hazard area; this decides whether a standard plan is possible.
  3. Note easements, power lines and where a new water meter could go.
  4. Collect permits for the house, garage and any additions.
  5. Take photos of all four sides of the house; the standard-plan checklist asks for them.
  6. Decide what you need: bedrooms, who will live there, and whether a conversion or a new detached unit fits better.

How RealHomes Helps Westminster Homeowners

RealHomes Construction (CSLB #1149773) builds ADUs and garage conversions across Orange County, including Westminster and Little Saigon. We check whether a standard plan fits your lot, prepare or coordinate the site-specific sheets, put the scope in writing and keep one point of contact through the final inspection. See our 8-step process, read the Garden Grove ADU requirements if you are comparing cities, or start with the 2026 California ADU laws.

Frequently Asked Questions

Does Westminster have pre-approved ADU plans?

Yes. The city offers six standard plans for detached ADUs, from 781 to 1,240 sq ft gross. They are about 85% complete, so you still need site-specific sheets prepared for your lot.

Can I convert my garage into an ADU in Westminster?

Yes. A conversion needs no new setbacks and no replacement parking. The standard plans are for detached ADUs, so a conversion goes through the regular plan check. Our guide to garage conversion ADU requirements covers the details.

Do I need a separate water meter for an ADU?

The standard-plan packet requires one for an ADU, while a JADU shares the home’s meter. Development Engineering can confirm what your lot needs.

Is there an impact fee for an ADU in Westminster?

ADUs under 750 sq ft are exempt from the park impact fee. Larger ADUs pay a fee proportional to the size of the main home, with a cap set by city ordinance.

Tóm tắt tiếng Việt

Westminster có 6 bản vẽ ADU tách rời mẫu đã duyệt sẵn (781 đến 1,240 sq ft), hoàn chỉnh khoảng 85% nên vẫn cần người thiết kế làm phần riêng cho lô đất; lô trong vùng ngập lụt không dùng được bản vẽ mẫu. Luật bang áp dụng: 1 ADU và 1 JADU trên lô nhà một gia đình, khoảng lùi hông và sau 4 ft, ADU tách rời cao ít nhất 16 ft, ADU gắn liền tới 25 ft; chuyển garage không cần lùi tường và không phải làm chỗ đậu xe thay thế. Bộ hồ sơ bản vẽ mẫu yêu cầu đồng hồ nước riêng cho ADU; cấm cho thuê 30 ngày trở xuống; ADU dưới 750 sq ft không đóng phí công viên. Nên hẹn Planning, Engineering và Building để sàng lọc trước, hoặc nộp online qua cổng Westminster Build. Gọi RealHomes (714) 657-9092 để được tư vấn ban đầu miễn phí, nói tiếng Việt.

This article is general information based on the City of Westminster ADU web page, the ADU Standard Plan Application Packet and Checklist (version 7, May 2025) and California Government Code Sections 66314 to 66342, as of October 2026. It is not legal advice. Rules and fees change; confirm current requirements with Westminster Planning at (714) 548-3247.